Procurement, RFPs and buying cooperatives
How you are allowed to buy a playground is decided before you know what you want to buy.
Short answer
Public playground purchases follow the buyer's procurement rules: informal quotes below a small dollar threshold, formal sealed bidding or an RFP above it, and sole source only with written justification. A cooperative purchasing contract can satisfy the competitive requirement because the lead agency already competed it, if your own rules and your funding source both allow it.
On this page
Your rules decide the route
Before design, before a wish list, find out three things: your own purchasing policy thresholds, whether the funding source imposes additional rules, and who has signature authority at each dollar level. Everything else follows.
| Route | When it applies | Award basis |
|---|---|---|
| Informal quotes | Small purchases, commonly under $5,000 to $50,000 | Documented quotes, usually three |
| Invitation for bid | Above the formal threshold, design fixed | Lowest responsive, responsible bid |
| Request for proposals | Above threshold, design to be proposed | Weighted score, price plus qualifications |
| Cooperative contract | Policy and funder allow it | Pre-competed pricing from a lead agency |
| Sole source | One legitimate supplier only | Written justification, approved in advance |
Thresholds exist to force competition at scale and to keep small purchases from costing more in process than in product. They are also what a challenge will be argued over, so get them from the purchasing officer in writing rather than from institutional memory.
RFP, RFQ, IFB and sole source
Invitation for bid (IFB). You publish a complete specification and a set of drawings. Bidders price it. Award goes to the lowest bidder who is responsive (bid what you asked for) and responsible (capable of doing it). Good when a designer has already fixed the layout and equipment schedule.
Request for proposals (RFP). You publish the site, the budget, the users and the outcomes you want. Vendors propose a design and a price. You score on published criteria. This is the normal route for playgrounds, because the design is the thing you are buying.
Request for qualifications (RFQ). You shortlist on experience and capacity with no price, then negotiate scope and fee with the top ranked firm. Common for design services, and required in some states for professional services. Note that some agencies use RFQ to mean request for quotation, which is the opposite. Define the term in your own document.
Sole source. One supplier can genuinely meet the need, most often when you are matching existing equipment for parts compatibility or extending a structure within its warranted system. It needs a written justification approved before you commit, and "we like their catalog" is not one.
Cooperative purchasing, and what it does not fix
A cooperative purchasing contract is an award that a lead public agency competed openly, written so other public agencies can buy from it. When your policy permits piggybacking, using one satisfies your competitive requirement without running your own solicitation, and it can cut two to four months from the schedule.
Three cautions.
- It does not select a design. Cooperative pricing is a discount off a published catalog from a specific supplier. If you have not done the design work, you have delegated it to a salesperson whose configuration will fill your budget precisely.
- Check what the contract covers. Many cover equipment only. Surfacing, site work, excavation and drainage often fall outside and still need their own procurement, which means two contracts and an interface to manage.
- Federal funds add a test. The Uniform Guidance procurement standards require you to document that the underlying contract was competitively awarded and that the price is reasonable. Keep the lead agency's solicitation, tabulation and award in your file.
Writing a scope of work that gets comparable bids
The scope is where the project is won or lost. Bids you cannot compare are worse than no bids.
Include, at minimum:
- Site. Survey or accurate plan, existing utilities, access route for trucks, staging area, grade change, soils information, and who owns spoil.
- Users. Age ranges served, expected peak occupancy, school or park context, supervision model.
- Required play events. By type and count, not by product. "At least two slides, one of which is accessible from a transfer platform, at least six swing bays including one adaptive seat, two independent spinning events".
- Fall height limit. State a maximum. This one number controls surfacing cost across the entire area.
- Surfacing. Material, required critical fall height rating, test method, depth or thickness, base and drainage responsibility, and the warranty term.
- Accessibility. Reference the 2010 ADA Standards for play areas and state the required counts of ground level and elevated components you expect. See ADA requirements.
- Standards compliance. Cite ASTM F1487 by edition and the CPSC handbook, and require a signed statement of conformance. CPSC, ASTM and standards explains what each document is and is not.
- Deliverables and schedule. Shop drawings, footing details, submittals, installation dates, and the weather assumptions behind them.
Evaluation criteria and weighting
Publish the weighting in the solicitation and score against it. Changing criteria after opening is the most common successful protest.
| Criterion | Typical weight | What you are actually testing |
|---|---|---|
| Price | 25 to 40% | Total installed, not equipment alone |
| Design and play value | 20 to 35% | Variety, circulation, age fit |
| Accessibility and inclusion | 10 to 20% | Beyond minimum counts |
| Experience and references | 10 to 20% | Similar sites, completed, checkable |
| Maintenance and warranty | 10 to 15% | Parts availability, term, exclusions |
Score design on what children will be able to do, not on rendering quality. Play value sets out the criteria that survive a scoring panel.
Require price on a common form. If one proposer excludes surfacing and another includes it, the scores are meaningless. A single bid form with the same line items as your budget breakdown solves it.
Warranty, installation, retainage and acceptance
Warranty language should separate structural components, moving parts, plastic and finish, because their terms differ by an order of magnitude. Ask what voids each one. Unsupervised volunteer installation commonly does.
Installation language should require a manufacturer-certified installer, specify footing depth and concrete strength, require as-built documentation, and state who verifies surfacing depth or thickness at completion. For a poured in place system, require in-place impact testing at defined locations before final payment; for loose fill, require documented installed depth after settlement.
Retainage of 5 to 10 percent held until acceptance is standard and is your only real leverage at the end. Define acceptance precisely: punch list complete, as-builts delivered, surfacing test results submitted, manufacturer certification of installation received, and an independent post-install audit passed by an inspector holding current certification. CPSI certification explains what that credential covers.
Keep the whole package. The solicitation, the award, the submittals, the test results and the audit are the file you will need in year six, filed the way maintenance records are kept.
What to do next
Sequence procurement against the rest of the project with the playground project timeline, because equipment lead times and weather windows will drive your award date more than your budget calendar will. Confirm your funding route first in funding a playground, since the money usually dictates the method. Then work through choosing an installer for the questions that separate a responsible bidder from a cheap one.
Frequently asked questions
Can we just buy from a cooperative contract and skip the bid?
Usually yes, if three things line up. Your own purchasing policy has to authorize cooperative purchasing, the cooperative's contract has to have been competitively awarded by a lead public agency, and your funding source has to accept it. Federal awards add their own test under the Uniform Guidance. Get the answer in writing from your purchasing officer before you rely on it.
What is the difference between an RFP and an invitation for bid?
An invitation for bid describes exactly what you want and awards to the lowest responsive, responsible bidder on price alone. An RFP describes the problem and the outcome, then scores proposals on stated criteria that include price and qualifications. Use an IFB when the design is already fixed. Use an RFP when you want the vendor to propose the design.
How do we avoid writing a spec that only one company can meet?
Specify performance and standards, not part numbers. Name the required fall height, age range, number and type of play events, accessible components, material finish and warranty term, then let bidders configure it. If you must reference a product to describe a feature, say the phrase your policy requires for an approved equal and define how equivalence is judged.
Who signs off that the finished playground complies?
The owner does, on the advice of someone qualified. Standard practice is an independent post-installation audit by a Certified Playground Safety Inspector who did not sell or install the equipment, plus the manufacturer's installation certification and as-built surfacing test data. Make that audit a condition of final payment in the contract, not a favor you ask afterward.
Should the same contract cover equipment and installation?
Generally yes. A single contract for supply and install removes the gap where a surfacing failure is blamed on the base and the base is blamed on the equipment footings. If your rules force separate contracts, write the interfaces explicitly: who sets grade, who signs off on footing depth, and who fixes drainage that ponds after both have left.
Sources
- 12 CFR Part 200, Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards. US Government Publishing Office, eCFRProcurement standards at 200.317 through 200.327 apply when federal money is involved
- 2Public Playground Safety Handbook. US Consumer Product Safety Commission, 2010Publication 325, the guidance most specifications reference
- 3ASTM F1487, Standard Consumer Safety Performance Specification for Playground Equipment for Public Use. ASTM InternationalThe consensus standard a specification should cite by edition
- 4Government Contracts: Construction (Davis-Bacon and Related Acts). US Department of Labor, Wage and Hour DivisionWage determination and certified payroll obligations on covered projects